A switchgear panel can look perfect and still fail on the day it is energized. A loose busbar joint, a reversed CT, a mis-wired interlock or a relay with the wrong setting will not show up on a visual inspection. They show up as a tripped incomer, a failed changeover, a burnt termination or, in the worst case, a fault the protection never sees.
Acceptance testing exists to find these problems while they are still cheap to fix. Fixing a wiring error on a workshop floor takes an hour. Fixing it on an energized site, with production waiting, costs days and carries safety risk. Yet on many Pakistani projects, factory and site testing are reduced to a short walk-through and a signature.
This guide sets out what a proper Factory Acceptance Test (FAT) and Site Acceptance Test (SAT) should cover for LV and MV panels, which parts of IEC 61439-1 apply, and how clients can witness testing in a way that actually protects them. It is written by the panel engineering team at Bilal Switchgear Engineering, an ISO 9001:2015 certified manufacturer.
FAT vs SAT: What Each Test Proves
FAT proves that the panel was built correctly to the approved drawings and specification. It is carried out in the workshop, where the panel can be energized safely at test voltages, wiring can be corrected quickly and the client’s engineer can inspect every compartment before the doors are closed for transport.
SAT proves that the panel survived transport and installation and works with the real cables, real earthing, real supply and real loads. Some things can only be verified on site: cable insulation, earth loop values, generator changeover under actual conditions and thermal behavior under load.
The two tests are complementary. A passed FAT does not excuse a skipped SAT, and a rushed SAT cannot replace a missing FAT, because many faults inside a panel are far harder to diagnose once it is installed and connected.
Where Routine Testing Fits: Type Test vs Routine Verification
IEC 61439 separates two kinds of verification. Design verification (the old ‘type test’) proves that a panel design meets requirements for temperature rise, short-circuit withstand, dielectric strength and similar properties. It is done once per design. Routine verification is done on every single assembly to prove that the unit built matches the verified design and has no manufacturing faults. FAT is the practical home of routine verification.
A client who asks for type-tested switchgear should therefore ask two questions: is the design verified, and will each delivered panel carry a routine test record? One without the other leaves a gap.
What a Proper FAT Covers for LV Panels
IEC 61439-1 lists the routine verifications for an assembly. In practice a thorough FAT for an LV switchboard or motor control centre includes the following.
1. Visual and Mechanical Inspection
Compare the built panel against the approved general arrangement and single line diagram: enclosure type and IP rating, busbar sizes, device ratings, nameplates, labelling, paint finish, door interlocks and cable entry arrangements. Check busbar joint torque against the manufacturer’s values and verify clearances and creepage distances where visible.
2. Protective Circuit Continuity
Confirm that every exposed conductive part (doors, frames, mounting plates, device bodies) is bonded to the main earth bar. The resistance between any exposed conductive part and the PE terminal should not exceed 0.1 ohm.
3. Dielectric Test or Insulation Resistance
For rated insulation voltages above 300 V up to 690 V, the power-frequency withstand test is 1,890 V AC for 1 second between live parts and exposed conductive parts. For assemblies with incomers up to 250 A, IEC 61439-1 allows insulation resistance measurement at 500 V DC as an alternative, with at least 1,000 ohm per volt of rated voltage to earth. Sensitive electronics must be disconnected or protected before any high-voltage test.
4. Wiring, Function and Mechanical Operation
Check every wire against the schematics (ring-out), then operate every device: breakers, contactors, selector switches, push buttons and indicators. Verify mechanical interlocks and key interlocks, and test withdrawable units for correct racking, shutters and position indication.
5. Protection Relay and Instrument Testing
Every protection relay should be tested by secondary injection: pick-up value, operating time at several multiples of setting, trip output and indication. This is covered in detail in our guide to protection relay panels. CT ratio and polarity should be checked, and meters verified against injected values.
Worked example: a feeder panel uses a 400/5 A CT. Injecting 100 A through the primary should give 100 / 80 = 1.25 A at the relay or meter terminals. A reading of 0.625 A means the wrong ratio tap is connected. A negative reading on a directional or power meter points to reversed polarity. Both faults pass a visual inspection and are only caught by injection.
6. Control Scheme and Sequence Tests
Run the control logic end to end: starter sequences, ATS and AMF changeover, trip and close circuits, alarm annunciation and interlock behavior. Simulate failures such as a lost auxiliary supply, a failed breaker or an open trip circuit, to confirm the panel behaves safely.
Additional FAT Tests for MV Switchgear
Routine tests for metal-enclosed MV switchgear under IEC 62271-200 go further. Typical items include power-frequency voltage withstand tests on the main circuit, tests on auxiliary and control circuits, measurement of main circuit resistance, mechanical operation tests, design and visual checks and, where specified, partial discharge measurement. For gas-insulated units, a gas tightness check is also part of the routine test programme. Test certificates should be issued per panel or per shipping section.
What a Proper SAT Covers on Site
Transport and Installation Checks
Inspect for transport damage, loosened busbar connections and moisture ingress. Re-torque joints that were disturbed when shipping sections were joined, confirm anchoring, and verify cable entry sealing and gland selection.
Cable and Earthing Verification
Test insulation resistance of every incoming and outgoing cable before connection, using a 5 kV tester for typical 11 kV cables and an appropriate lower voltage for LV cables, with any DC or VLF high-voltage test carried out according to the cable manufacturer and consultant specification. Measure earth electrode and earth loop values and confirm continuity of the panel earth bar to the site earthing system.
Protection and Scheme Re-Verification
Check that relay settings loaded on site match the approved coordination study. Where practical, perform primary injection on key circuits to prove the CT, wiring, relay and breaker chain as a whole. Repeat ATS and AMF changeover tests with the real generator and real loads.
Thermography Under Load
After the panel carries real load, scan busbar joints, breaker terminals and cable lugs with a thermal camera. Loads of at least 40 percent of rated current are the usual minimum for a meaningful scan, and higher is better. A joint running noticeably hotter than identical joints on the same phase group is a defect to correct, even if it is within absolute limits.
How to Witness a FAT Effectively
Step 1: Agree the test plan in advance
Request the test procedure and acceptance criteria at the order stage, not on the day. A good plan lists every test, the instrument used and the pass limit.
Step 2: Check instrument calibration
Insulation testers, injection sets and multimeters should carry current calibration certificates. A test with an uncalibrated instrument proves little.
Step 3: Witness the critical tests personally
Prioritise dielectric or insulation tests, protective circuit continuity, relay injection and interlock operation. These are the tests most often skipped under time pressure.
Step 4: Record punch items and close them out
Every observation goes on a numbered punch list with an owner and a closing date. Do not release the panel for dispatch with open safety items.
Common Findings at FAT
The same categories of defect recur on panels from every builder, which is exactly why testing matters:
- Busbar and terminal joints below the specified torque
- CT ratios or polarity different from the schematic
- Relay settings left at factory defaults instead of the study values
- Interlock or key sequence not matching the approved scheme
- Wire numbers or labels that do not match the drawings
- Missing or damaged paint, gland plates or door seals affecting IP rating
- As-built drawings that differ from the built panel
The Documentation You Should Receive
- Signed FAT report with every test result, instrument serial numbers and calibration dates
- Routine test certificate per panel or shipping section
- Relay settings schedule and secondary injection records
- As-built drawings: single line diagram, schematics, general arrangement and wiring diagrams
- Bill of materials with component makes and ratings
- Design verification (type test) evidence for the assembly
- SAT report with cable test values, earth readings, thermography images and punch list closure
Panel Testing at Bilal Switchgear Engineering
Our Power Division tests every panel before dispatch under our ISO 9001:2015 quality system, with test records retained for each project. Clients are invited to witness FAT at our Lahore works, and we support site commissioning with SAT checks and handover documentation.
This applies across our LV type-tested switchgear, MCC, PFI, ATS and MV panel ranges.
Contact our engineering team to request a sample FAT procedure for your project or to schedule a witnessed test.
Frequently Asked Questions
What is the difference between FAT and SAT?
FAT is performed at the manufacturer’s works before dispatch and proves the panel was built correctly to the approved design. SAT is performed on site after installation and proves the panel works correctly with the real cables, earthing, supply and loads. Both are needed, because some faults can only be found in each environment.
Is FAT mandatory for electrical panels in Pakistan?
IEC 61439 requires routine verification on every assembly, and FAT is where this is normally done. Whether a witnessed FAT is contractually mandatory depends on the project specification, consultant and client. For industrial, hospital and utility-connected projects it is usually specified, and DISCO or consultant approval may require test records.
What insulation test is done on an LV panel at FAT?
For rated insulation voltages above 300 V up to 690 V, IEC 61439-1 specifies a power-frequency withstand test of 1,890 V AC for 1 second. For assemblies with incomers up to 250 A, an insulation resistance measurement at 500 V DC, at least 1,000 ohm per volt of rated voltage to earth, is permitted as an alternative.
Why is secondary injection testing of relays necessary?
Secondary injection applies simulated currents or voltages directly to the relay inputs to confirm pick-up values, operating times and trip outputs. It is the only practical way to prove a relay is set and wired correctly before the panel is energized. It must be repeated after any setting change.
Can a client skip SAT if FAT was passed?
No. Transport, handling and installation can loosen connections or damage components, and site conditions such as cable quality, earthing and generator behavior cannot be verified at the factory. SAT is the final proof that the complete installation works safely.